Good news from the ATC, regarding the AT walking bridge across the Potomac River.
CSX and NPS have announced that they plan to start work on the walking bridge across the river within the next two weeks, with hopes of opening it by the end of June.
Good news from the ATC, regarding the AT walking bridge across the Potomac River.
CSX and NPS have announced that they plan to start work on the walking bridge across the river within the next two weeks, with hopes of opening it by the end of June.
Most Awesome!
Plaid is fast! Ticks suck, literally... It’s ok, bologna hoses off…
Follow my hiking adventures: https://www.youtube.com/user/KrizAkoni
Follow me on Instagram: https://www.instagram.com/alphagalhikes/
Very cool, and good to hear!
willin'
The old bridge crossed the Potomac river.
"That's the thing about possum innards - they's just as good the second day." - Jed Clampett
Some surprising good news. Frankly I'm stunned they're getting it done so soon.
Ironically, no one might be allowed to visit the park and walk the bridge anytime soon...
Be Prepared
Does the end of June still look likely?
UPDATE (06/21/2020): CSX railroad is finally working on the bridge in Harpers Ferry. They started a couple of weeks ago. It took them longer to get the permits, imagine that. Estimated finish time is now the latter part of July.
CSX is also supposed to be starting shuttling from HF around the C&O to Maryland but the're still waiting for that to happen.
Here is a photo of the progress from 10 days ago.
102944397_273755573776273_1580788840684768316_n.jpg
Great shot